Alumina refineries: Guinea is industrialising its bauxite

Three alumina refineries are under construction in Guinea — SPIC (Boffa), WCAG (Boké) and Chalco (Boffa), 1.2 Mt/yr each — while the only existing plant, Fria, dates from 1960. The state targets 5 to 6 refineries by 2030 (~7 Mt/yr). Dated official announcements, source gaps reported, missing links named.

● Verified announcements — press & statements● Target: 5-6 refineries by 2030Updated 31 Oct 2026
ShareWhatsAppTelegramFacebook

01 Key figures

3
Refineries under construction
SPIC 03/2025 · WCAG 12/2025 · Chalco 06/2026
1.2 Mt/yr
Announced capacity for each
SPIC, WCAG and Chalco — official announcements
5-6
Plants targeted by 2030
≈ 7 Mt/yr — mines minister (Reuters, 12/11/2025)
1
Existing refinery (Fria)
1960 — Africa's first, ~600 kt/yr capacity

02 The plan: 5-6 refineries by 2030

On 12/11/2025, Mines Minister Bouna Sylla announced the target: build 5 to 6 alumina refineries by 2030, lifting local processing capacity to about 7 million tonnes per year (Reuters via Guinéenews, 12/11/2025). His line: 'No refinery has been built since the colonial era. That is about to change.'

Context recalled by La Tribune (15/12/2025): Guinea holds about a third of world bauxite reserves, exported 145 Mt of bauxite in 2024 — and operates only one refinery, at Fria. In June 2026 the ministry restated: 'five refineries by 2030… we are at 3' (mines.gov.gn, 14/06/2026).

Reading: exporting raw ore (~USD 30/t average 2025, see the reference price page) or processing locally changes the value captured per tonne — and the revenue level documented on the taxes page.

03 The three sites, project by project

ProjectBackersLocationAnnounced capacityAnnounced investmentWorks / target
SPICSPIC (China, state-owned)Boffa1.2 Mt/yr≈ USD 1bn (agreement Dec 2024)since 26/03/2025 · end-2027
WCAGWinning Shipping + Shandong Weiqiao + UMSDobali (Boké)1.2 Mt/yr>USD 1.2bn (Presidency) — ~USD 1bn (Mines)since 12/12/2025 · end-2028
CHALCOChalco Hong Kong (CHINALCO)Lisso-Démougala (Boffa)1.2 Mt/yrUSD 1.68bn (official) — ~USD 1bn (Bloomberg)since 13/06/2026 · n.p. (works end 2029)

Sources: dated official announcements — presidence.gov.gn and mines.gov.gn (12/2025, 06/2026) · primature.gov.gn (17-18/08/2026 for SPIC) · Reuters/Guinéenews (12/11/2025) · Africaguinee (14/06/2026). Discrepancies between official sources are reported, never merged.

  • SPIC (Boffa) — 'the first since independence': ~USD 1bn agreement signed in late December 2024 (Guinéenews, 30/12/2024); works started 26/03/2025. Announced components: 250 MW captive power plant (100 MW to the grid), 35,000 t wharf, 600 direct jobs (Guinéenews, 28/03/2025). The project's water reservoir was declared of national interest by decree on 16/06/2026 (Mosaïqueguinée); progress review with the Prime Minister on 17/08/2026 (primature.gov.gn). Commissioning announced for end-2027.
  • WCAG (Dobali, Boké) — 'the second' (mines.gov.gn, 12/2025): shareholders Winning Shipping Ltd (Singapore), Shandong Weiqiao (China) and UMS (Guinea); works launched 12/12/2025 under the Simandou 2040 strategic committee. Announced ~300 MW power plant; 10,000 to 12,000 direct and indirect jobs depending on the source. Commissioning announced for end-2028.
  • CHALCO (Boffa) — 'the third' (mines.gov.gn, 06/2026): amended and consolidated mining agreement signed 21/05/2026; works launched 13/06/2026 at Lisso-Démougala (~40 km from Boffa); ratified by ordinance on 03/07/2026 then approved by the National Assembly on 03/08/2026, with reservations over state guarantees. CHINALCO's first alumina refining project outside China. ~1,000 direct and 12,000 indirect jobs announced; 500 scholarships over 20 years and an engineering school in the programme (DCI via Guinéenews/Guinee7, 22/05/2026). No detailed delivery schedule published (Africtelegraph, 23/05/2026); works completion announced for 2029 (36-month duration — Africaguinee, 14/06/2026).
If the three projects meet their announcements, combined capacity would reach ≈ 3.6 Mt/yr, about half of the 2030 target [own calculation: 3 × 1.2 Mt/yr]. Next in line: Alteo (project declared of national interest on 21/03/2024, still at design stage), CBG (works targeted before end-2026 — CBG statement, 31/08/2026), Alcoa under discussion, and state-owned NMC targets a unit by 2030 (Agence Ecofin, 05/05/2026).

04 Fria: the only existing plant (1960)

The country's only alumina refinery was built by Péchiney and inaugurated on 30 April 1960 at Fria — Africa's first alumina plant (Wikipedia, consulted 02/09/2026). Official capacity: 600,000 t/yr (Rusal), up to 650,000 t/yr per other sources; actual output estimated between ~400,000 and ~450,000 t/yr in 2022-2023 (Guinee7).

  • 2012-2018: shutdown after the April 2012 strike; production quietly restarted in 2018 (Jeune Afrique, 06/2018).
  • 2025: per the Guinean press, the state has held 100% of the shares since February 2025, after the end of the lease-management agreement signed with Rusal in 2000 [single source — GuinéeQuotidien, 07/06/2025]; strikes in July 2025; the plant was still running in December 2025 (Guinee7, Guineelive).
The precedent of promises: 'almost all bauxite exporters have used the promise of building a refinery since 1963… 60 years on, only one refinery exists' (Guinee7, 17/04/2022). GAC had promised a ~2.8 Mt/yr plant (expandable to 4.5) without ever building it — its Sangarédi concession was transferred to state-owned NMC in 2025.

05 Why now

Three forces converged in 2025-2026:

  • Falling bauxite prices: world prices lost 20 to 35% versus their 2025 peaks (Reuters, 16/03/2026). See the 2026 context on the reference price page →
  • Export restrictions: Guinea announced it would curb bauxite exports from April 2026 to support prices (Reuters, 18/03/2026) — export less, process more.
  • Pressure on operators: the suspension of GAC's exports in mid-2024 was part of 'broader pressure on bauxite operators to commit to building alumina refineries' (Agence Ecofin, 06/05/2026). GAC lost its concession in 2025; an amicable settlement was announced on 06/05/2026.
Refining changes the structure of revenues: it shifts value from raw ore (~USD 30/t) to an industrial product. The taxes → and exports → pages document the current base these plants are meant to process.

06 What we know / what we don't know

  • We know: the official target (5-6 plants, ~7 Mt/yr — 12/11/2025) · the three launched sites and their announced capacities (1.2 Mt/yr each) · the discrepancies between official figures (WCAG: ~USD 1bn vs >USD 1.2bn; Chalco: ~USD 1bn vs USD 1.68bn) · only one existing refinery (Fria, 1960) · the Chalco ratification calendar (ordinance 03/07/2026, National Assembly 03/08/2026).
  • We don't know: the actual physical progress of the sites (no independent monitoring published — no WCAG follow-up article between 12/2025 and 09/2026) · the state's stake in SPIC and WCAG (not published) · Fria's actual output since 2024 · the capacity and cost of the CBG and Alcoa projects (not published) · Chalco's detailed schedule · the status of the state's participation option in Chalco (5% free of charge, option up to 35% — Bloomberg via Construction Review, single source).
Where to verify: official statements (presidence.gov.gn, mines.gov.gn, primature.gov.gn) · dated press (Reuters, Guinéenews, Agence Ecofin, Africaguinee) · EITI reports once the plants are in production. This page is updated with every verified source.